Pengaruh Addendum Terhadap Waktu Penyelesaian Pekerjaan Pembangunan Drainase

Authors

  • Nova Nevila Rodhi Universitas Bojonegoro
  • Bayu Santoso Putra Program Studi Teknik Sipil, Universitas Bojonegoro

Keywords:

Addendum, Waktu, Regresi Linier

Abstract

An addendum is a contract that contains changes to several agreed work items, both technical and non-technical. An addendum occurs when both parties in the relevant agreement agree on specific reasons. Nowadays, it is expected to find changes in a contract agreement, in this case, a construction project contract agreement. The existence of an addendum can affect the goals of a construction project, especially in terms of time and cost. This research aims to analyze the influence of the addendum on project implementation time for drainage construction in Bojonegoro Regency using the Linear Regression method. The data in this research were obtained from distributing questionnaires using a purposive sampling method to qualified respondents according to the research objectives. The analysis results show that the factors causing the addendum to the work completion time are 22.4%, while other factors influence the rest.

ABSTRAK:
Addendum merupakan sebuah kontrak yang berisikan adanya perubahan beberapa item pekerjaan yang telah disepakati, baik itu secara teknis maupun non teknis. Addendum terjadi ketika terdapat sebab-sebab tertentu yang telah disepakati kedua belah pihak yang bersangkutan dalam perjanjian terkait. Dewasa ini, tidak jarang ditemukan perubahan dalam suatu perjanjian kontrak yang dalam hal ini adalah perjanjian kontrak proyek konstruksi pembangunan. Adanya addendum dapat mempengaruhi tujuan proyek konstruksi, terutama dalam hal waktu dan biaya. Penelitian ini bertujuan untuk menganilisis pengaruh addendum terhadap waktu pelaksanaan proyek pada pembangunan drainase di Kabupaten Bojonegoro dengan metode Regresi Linier. Data pada penelitian ini diperoleh dari hasil penyebaran kuesioner dengan menggunakan metode purposive sampel pada responden yang memiliki kualifikasi sesuai tujuan penelitian. Dari hasil analisis diketahui bahwa faktor penyebab addendum terhadap waktu penyelesaian pekerjaan sebesar 22,4% sedangkan sisanya dipengaruhi oleh faktor lain.

References

Suripin, Sistem Drainase Perkotaan yang Berkelanjutan, Yogyakarta: Andi Offset, 2004.

W. Tejakusuma, O. T. Purwadi and Sumiharni, "Analisis dan Perencanaan Sistem Drainase di Lingkungan Universitas Lampung (Studi Kasus Zona II : Fakultas Matematika dan Ilmu Pengetahuan Alam, Fakultas Kedokteran dan Fakultas Keguruan dan Ilmu Pendidikan)," JRSDD, vol. 6, no. 2, pp. 1 - 8, 2018.

R. J. Kodoatie and R. Syarif, Tata Ruang Air, Yogyakarta: ANDI, 2010.

M. Khamim and W. Harsanti, "Analisis Penyebab Addendum Dan Pengaruhnya Terhadap Efektivitas Sasaran Proyek Pembangunan Gedung Di Kota Malang," PROKONS: Jurnal Teknik Sipil, vol. 12, no. 1, pp. 8 - 15 , 2018.

S. A. Gumolili, B. F. Sompie and J. P. Rantung, "Analisa Faktor-faktor Penyebab Change Order Dan Pengaruhnya Terhadap Kinerja Waktu Pelaksanaan Proyek Konstruksi Di Lingkungan Pemerintah Provinsi Sulawesi Utara," Jurnal Ilmiah Media Engineering, vol. 2, no. 4, pp. 247-256, 2012.

A. K. Muhammad, P. A. Henny and R. Abdul, "Analisis Contract Change Order Pada Pelaksanaan Proyek Apartemen Alton Semarang," Wahana Teknik Sipil: Jurnal Pengembangan Teknik Sipil , vol. 26, no. 2, pp. 222 - 234, 2021.

D. Annisa, J. A. Sitorus, N. M. Putri and N. Achmad, "PEntingnya Sebuah Addendum Dalam Keberlangsungan Suatu Proyek Pembangunan," UPN Veteran Surabaya, Surabaya, 2021.

J. N. Desai, J. Pitroda and A. J. Bhavsar, "A Review On Change Order And Assessingcauses Affecting Change Order In Construction," Journal Of International Academic Research For MULTIDISCIPLINARY, vol. 5, no. 12, pp. 152-161, 2015.

H. E. Putra and H. Sulistio, "PENgaruh Change Order Terhadap Biaya, Mutu, Dan Waktu Pada Proyek Konstruksi Gedung Bertingkat," JMTS: Jurnal Mitra Teknik Sipil, vol. 3, no. 4, pp. 1349 - 1362, 2020.

B. M. Nasrul, "Tinjauan Addendum Waktu Pelaksanaan Proyek Pembangunan Jembatan Kampung Baru Nan XX Kota Padang," Jurnal Universitas Muhammadiyah Sumatera Barat, vol. 2, no. 2, 2019.

D. I. O. Riani, " Pelaksanaan Addendum Perjanjian Pembangunan Pasar Seketeng Kabupaten Sumbawa Antara Bapenda Kabupaten Sumbawa Dengan PT. CITRA PERSADA, KSO," Universitas Mataram, Mataram, 2020.

R. D. Dharmawan, H. A. Safarizki and A. A. Firdausi, "evaluasi efektivitas keputusan addendum proyek terhadap waktu pekerjaan proyek berbasis earned value method," J@ti Undip: Jurnal Teknik Industri, vol. 18, no. 1, pp. 51-61, 2023.

W. Harsanti, "Analisis Penyebab Addendum dan Pengaruhnya Terhadap Efektivitas Sasaran Proyek Pembangunan Gedung di Kota Malang," Prokons: Jurnal Teknik Sipil, vol. 12, no. 1, pp. 8-15, 2019.

A. Martanti and S. Hardjomuljadi, "The Effect of Contract Change Order on Contractor Financing in Government Projects," International Journal of Civil Engineering and Technology, vol. 9, no. 6, p. 665–671, 2018.

R. Putri, V. Puspita and Y. Simamora, "Analisis Faktor Penyebab, Akibat, dan Proses Contract Addendum Proyek Konstruksi Jalan Kota Palangkaraya.," Jurnal Teknika,, vol. 2, no. 2, pp. 136-147, 2019.